Christmas Refurbishment @ NASAM – As At 28 Dec 18

Christmas Refurbishment @ NASAM – As At 28 Dec 18 Day 16 since the refurbishment of the shop started; ceiling and walls painted, cabinets and counter painted and installed, electrics and electronics ready for finishing.  And, thanks to the sterling work of all the volunteers involved, the project is on schedule. The 28th December saw the local […]

Christmas Refurbishment @ NASAM – As At 28 Dec 18 Read More »

Christmas Refurbishment @ NASAM – As At 27 Dec 18

Christmas Refurbishment @ NASAM – As At 27 Dec 18 Sorry but I have lost track of how many days we have been doing this now (on the 27th, it was the 15th day since the refurb started .. Ed ..). Today saw the last of the cabinets painted, plus the new book display unit installed

Christmas Refurbishment @ NASAM – As At 27 Dec 18 Read More »

Christmas Refurbishment @ NASAM – as at 23 Dec 18

Christmas Refurbishment @ NASAM – (as at 23 Dec 18) Progress has been continuing at the Norfolk and Suffolk Aviation Museum on the shop renovation throughout the week since the last update.  The following updates were sent in by volunteers who are continuing to carry out the work. Update on the 20th December 2018, the new cabinets

Christmas Refurbishment @ NASAM – as at 23 Dec 18 Read More »