Christmas refurbishment @ NASAM – 18 Dec 2018
Day seven of the shop refurbishment and the fourth major day of volunteer work has now finished.
The electricians have removed all of the old wiring, and the new supply is in place. We do have lights in the shop, but no other power yet.
All of the cabinets that were removed from the shop on day two, and are being reused, have been modified and a primer coat applied.
A primer coat of paint has also been applied to the boards which will cover the walls.
The ladies, gents and accessible toilets have all been decorated ready for the new hand driers to be installed.
All in all another good day of progress.
Images from the Day
Author:: Steve Bell